Date of Submission
| S.No. |
Outputs |
Time Period |
Date(As Per Schedule) |
Extended/Tentive Date |
| 1 |
Inception Report (including report of Kick off workshop) |
At the End of Week 6 |
12th November 2009 |
30th November 2009 |
| 2 |
Sector Analysis Report and City Profile |
At the End of Week 12 |
24th December 2009 |
6th January 2010 |
| 3 |
Report of 2nd Workshop on City Vision and Sector Goals |
At the End of Week 15 |
14th January 2010 |
27th January 2010 |
| 4 |
Report of the 3rd Workshop on Strategy and Priority Projects |
At the End of Week 18 |
4th February 2010 |
17th February 2010 |
| 5 |
Draft CDP and City Level Workshop |
At the End of Week 21 |
25th February 2010 |
10th March 2010 |
| 6 |
Final CDP |
At the End of Week 24 |
18th March 2010 |
31st March 2010 |
Note : Consultant shall start the Services on 1st October 2009 and shall complete them by
18th of March 2010 (As Per Agreement)